1. Generally, the reinforcement processing shed is within the lifting range of the tower crane. Otherwise, it is inconvenient to lift the reinforcement. 2. There are two layers on the top of the protective shed. The formwork is laid on the uppermost compartment and two layers of bamboo sheets are laid on the lower layer. The spacing between the two floors is 500 mm. There is a 500 high enclosure on the top surface. It is erected with double steel pipes as columns. 3. There are fire extinguishers, reinforcement processing equipment and lighting system inside. 4. There are name plates at the door and operating procedures and precautions next to the machinery.
What are the standards for reinforcement processing shed